Central Insecticide and Fertilizers Private Limited is coming up with Tecnical Grade Pesticide Unit Project at Sikar, Rajasthan - Expansion.The Indian pesticides industry is characterized by low capacity utilization. The present total installed capacity is 146,000 tonnes and has a low capacity utilization of< 60%.The design capacity of the proposed plant will be 500 MTA.
It is proposed to manufacture two Pesticide products on a daily basis based on the prevailing market requirement. The power requirements will be 300 KVA. DG set of capacity 300 KVA will be used in the plant for power back up. The permission for 300 KVA power supply from electricity board will be obtained Fixed foam system with adequate capacity. Total cost of the project is Rs. 6 crores only.
As of September 2023, The project is now in the stage of construction being started the work on the project will be finished in 2024, 2025 or 2026 It has been decided to hire a local contractor.
Newsby Rahul Yeligetti