GMLR Update: Dual-Tunnel Excavation Now Fully Active

Major milestone for Mumbai's infrastructure! Tunnel excavation on the Goregaon-Mulund Link Road (GMLR) project beneath Sanjay Gandhi National Park is now fully active.

With TBM Tulsi already having bored past the 270-metre mark from the Goregaon side, the second machine, Vihar, officially started digging on 7 November 2026 following its successful Site Acceptance Test. Once complete, these twin three-lane tunnels will significantly cut travel time between Mumbai's western and eastern suburbs.

 

News by Rahul Yelligetti.

 