Current Date: 11 Sep, 2026

Gurgaon-Pataudi-Rewari Highway Moves Closer to Full Opening

The National Highways Authority of India (NHAI) has commenced partial trials on the 43.8-km Gurgaon-Pataudi-Rewari highway, allowing traffic on completed stretches as work continues on the remaining sections.

The four-lane corridor, with two-lane service roads on both sides, includes 19 flyovers and a railway overbridge at Pahari. Additional sections are expected to open in the coming months as major structures are completed.

Work on the Dwarka Expressway flyover has been delayed due to the relocation of a 400kV transmission line owned by Delhi Transco. The line is expected to be shifted by November, paving the way for the remaining structural and approach works.

 

News by Rahul Yelligetti.

 

Share

Source : projxnews