Trial runs have begun on Bengaluru Metro's Blue Line (Phase 2A) as of November 24, with initial testing spanning four stations from KR Puram towards Mahadevpura.
According to Greater Bengaluru Development Minister Krishna Byre Gowda, the 19.75-km KR Puram–Central Silk Board section is slated to open by mid-2027. Spanning 58.32 km in total at an estimated ₹20,000 crore, the full Blue Line will link Central Silk Board to Kempegowda International Airport via hubs like Marathahalli, KR Puram, Hebbal, and Yelahanka.
The expansion supports the state's push to grow Bengaluru's operational Metro network to 176 km by 2027 and 500 km by 2037, improving airport access and easing city traffic.