Nagpur Metro’s Phase II expansion towards Transport Nagar has hit a major construction milestone, with overall corridor progress reaching 78%. Foundation work is now complete across the entire 5.33 km Reach 4A viaduct, and track laying has begun on a 1 km stretch. Extending the Aqua Line from Prajapati Nagar and H B Town to Transport Nagar, the corridor will feature three elevated stations—including Pardi—and a 2 km double-decker viaduct over the existing Pardi flyover. Executed by Kalpataru Projects International since November 2024, the project is currently using three launching girders to complete viaduct works by July 2027, eventually boosting connectivity to Kalamna Market, local industrial zones, and Symbiosis University.