Mission Polavaram: Phase-1 Finish Line Set for March 2027

Chief Minister N Chandrababu Naidu has expressed confidence that Phase-1 of the Polavaram Irrigation Project will be completed by March 2027, following an inspection of progress at the Polavaram site.

During a review meeting with senior officials and contractors, the Chief Minister confirmed that the earth-cum-rock fill (ECRF) dam under Phase-1 will be set at 119 tmc-ft, enabling gravitational flow of water to the intended regions. He also stressed that resettlement and rehabilitation of affected families must be completed by January 2027. The new diaphragm wall (D-wall), built at a cost of nearly Rs 1,000 crore, has achieved 81 per cent completion.

The Chief Minister stated that Phase-2 of the project will commence after the completion of Phase-1 and is scheduled to be completed by 30 June 2027. He also highlighted progress on connectivity works, noting that the twin tunnels are expected to be completed by June 2026.

 

News by Rahul Yelligetti.

 